Former Member

Project Progress Catch-up Plan

Dear PS Friends,

I would like to know if any of you have worked on Project Progress Catch-up Plan.

Basically, it is the third dashed-curve which comes in a project progress graph of plan vs actual to cover u2013up the delay.

Below is an example to explain this.

M3 being the current month.

Months	M1	M2	*M3*	M4	M5	M6	M7	M8	M9
Plan PoC	0%	12%	20%	35%	42%	52%	60%	72%	90%
Actual PoC	2%	7%	12%						
Catch-up			12%	18%	24%	40%	52%	72%

If yes, please let me know and also how we can implement in SAP PS.

Thanks in advance for your help!

Regards,

Aparna

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jul 03, 2011 at 07:04 AM

    did you check the SAP help for Project Progress analysis especially for the following..

    EAC.

    SV.

    CV.

    Add comment
    10|10000 characters needed characters exceeded

    • I doubt whether your requirement can be met through project progress..

      SAP Help clearly mentioned that the basis for EVA is BCWS, BCWP and ACWP, where as in your case there is no cost.. so none of this curve will work.

      I think Better to go for a Z development of your own EVA method based only on the date.

  • Jul 19, 2011 at 06:53 AM

    hi,

    try reduction startegy and check if that helps you.

    vengaiah

    Add comment