on 06-30-2011 7:04 PM
Hi
In our factory there are 15 operations (15 filling machines= 15 Resources) that works in same times " Start-Start" and machine time was given as per Machine (ex.1H/50EA)
1- I created the 15 Resources with standard formulas of scheduling SAP002= (SAP_02 * SAP_09 / SAP_08 / SAP_11)
2- I created my Master recipe with the 15 operations and the 15 phases (Relationship= S-S)
3- Now if i created Prod order for 1000EA
=> i m surpised that the system does not execute the correct scheduling!!!
the result of my parametre is:
to produce 1000EA the system required 20 H for each operations start at 30/06/11 06h00:00 and finished at=start day +20h
But in reality : to produce 1000EA with 15 machines we need = (Req time for one machine/15machines) =20h/15= 1.33H
How can we configure this..in scheduling purpose
Please note that we working by the master recipe C202 and I searched in the details for operation in order to find the zone where we can maintain the split number (does not exist)
Best regard
Hi,
IF all the 15 machines are exactly the same and doing the same task, you only need to create single resource and maintian individual capacity as 15 in resource.
Your master reciepe will have single opertion with single phase. check and revert,
Santosh Sarda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Santosh Sarda,
thanks a lot Santosh,I already adopt this solution " my question is how to config the spliting parallel operation"
please refer to the initial question for more details
we decide on the parallel operation in order to reduce the Nbre of PO per day. If I do this configuration u201Cone resource by Master recipeu201D we will have more than 150 PO per day =>really itu2019s hard to manage it .
i will be thankful if you help me to solve this issue
Many thank
Hi,
I guess you would have created 15 Parallel sequences one each for each Resource. Looks like operation qty split does not work for parallel sequencing operations. Each Sequence shows same number of opertaion qty as of order qty.
Parallel sequences i guess are only maint to perform different activities simulataniously. However same number of order qty needs to pass through each sequence .
Only solution for you is to use Operation qty splilt by maintaining individual capacities in Resourse or to create different process order for each resorce.
http://www.sapfans.com/forums/viewtopic.php?f=9&t=266662
Check and Revert,
Edited by: santosh sarda on Jul 1, 2011 7:22 PM
Hi
As per my understanding you have to maintain overlapping between operation
in the operation overview screen go for overlapp tab and select continous prodcution, and min ahead qty or minahead time.
Please check and come back.
Regards,
srihari.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.