cancel
Showing results for 
Search instead for 
Did you mean: 

Spliting parallel operation in Master recipe C202

0 Kudos

Hi

In our factory there are 15 operations (15 filling machines= 15 Resources) that works in same times " Start-Start" and machine time was given as per Machine (ex.1H/50EA)

1- I created the 15 Resources with standard formulas of scheduling SAP002= (SAP_02 * SAP_09 / SAP_08 / SAP_11)

2- I created my Master recipe with the 15 operations and the 15 phases (Relationship= S-S)

3- Now if i created Prod order for 1000EA

=> i m surpised that the system does not execute the correct scheduling!!!

the result of my parametre is:

to produce 1000EA the system required 20 H for each operations start at 30/06/11 06h00:00 and finished at=start day +20h

But in reality : to produce 1000EA with 15 machines we need = (Req time for one machine/15machines) =20h/15= 1.33H

How can we configure this..in scheduling purpose

Please note that we working by the master recipe C202 and I searched in the details for operation in order to find the zone where we can maintain the split number (does not exist)

Best regard

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

IF all the 15 machines are exactly the same and doing the same task, you only need to create single resource and maintian individual capacity as 15 in resource.

Your master reciepe will have single opertion with single phase. check and revert,

Santosh Sarda

0 Kudos

Hi

I m gree with you but with this configuration "one resource with 15 nbre of capacitie we will lose the visibility on these machines.

and our factory manager wants to follow the scrap, breakdown time and efficiency line per machine.

is there another solution?

regards

Foued

Former Member
0 Kudos

Hi,

I think you have to go for parallel sequences in mastre receipe. Not sure if you can use operation splitting. Otherwise create separate process order for each resourse,

Regards,

Santosh Sarda

0 Kudos

Hi Santosh Sarda,

thanks a lot Santosh,I already adopt this solution " my question is how to config the spliting parallel operation"

please refer to the initial question for more details

we decide on the parallel operation in order to reduce the Nbre of PO per day. If I do this configuration u201Cone resource by Master recipeu201D we will have more than 150 PO per day =>really itu2019s hard to manage it .

i will be thankful if you help me to solve this issue

Many thank

Former Member
0 Kudos

Hi,

I guess you would have created 15 Parallel sequences one each for each Resource. Looks like operation qty split does not work for parallel sequencing operations. Each Sequence shows same number of opertaion qty as of order qty.

Parallel sequences i guess are only maint to perform different activities simulataniously. However same number of order qty needs to pass through each sequence .

Only solution for you is to use Operation qty splilt by maintaining individual capacities in Resourse or to create different process order for each resorce.

http://sap.ittoolbox.com/groups/technical-functional/sap-acct/quantity-split-for-parallel-operations...

http://www.sapfans.com/forums/viewtopic.php?f=9&t=266662

Check and Revert,

Edited by: santosh sarda on Jul 1, 2011 7:22 PM

Former Member
0 Kudos

Hi

As per my understanding you have to maintain overlapping between operation

in the operation overview screen go for overlapp tab and select continous prodcution, and min ahead qty or minahead time.

Please check and come back.

Regards,

srihari.M

0 Kudos

Hi,

I don't find where we can maintain these notion in C202

could you please guide me

thanks

Foued