Preparation activities for EHP4 upgrade in MSCS

Dear Experts,

I am going to start the EHP4 upgrade on ECC 6 in HA environement.

Can you plese let me know the specific preparation steps to be done before starting the EHP4 upgrade in HA environment.

We are running on windows server 2008.

I went through the EHP4 installation guide.It is mentioned that "disable the cluster fail over capabilities before starting the EHP installation".

In our scenario,

We have CI Node with ASCS and SCS in SAP cluster group and CI installation in local drive.

and DB node with ORA group and DI installation in local drive.

So to disable the automatic cluster fail over capabilities, is it sufficient to move the ORA group on DB node to CI node and pasue the db node in cluster administrator?

Please confirm if I am correct and let me know if there are any other preparation steps to be done in cluster environment for EHP upgrade.

Regards,

Edited by: mutnuru dinakar on Jun 30, 2011 2:47 PM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jun 30, 2011 at 01:33 PM

    >>So to disable the automatic cluster fail over capabilities, is it sufficient to move the ORA group on DB node to CI node and pasue the db node in cluster administrator?

    This should be OK, as during upgrade your SAP and DB may be restarted and if your cluster is up then it may fail to another node which can cause issue while upgrade.

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 30, 2011 at 03:25 PM

    It is not sufficient to do that - you MUST move all the resources onto the single node and disable all the cluster services.

    You run the application as if it is not part of a cluster - that means starting the database and the SAP application as you would on a normal server.

    if you have the cluster running it may suffer an unrelated failure which will cause it to fail over and screw up your upgrade.

    I have done several upgrade projects on Windows Clustering and this is the SAP way of running upgrades on Windows HA platforms

    Thanks

    Chris

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 30, 2011 at 05:10 PM

    Hi,

    Additionally, you can check SAP Note 1012486- Important Information on upgrading SAP Systems in HA-Setups

    Thanks

    Sunny

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Once you move all the resources to your CI node, all you have to do is pause the db node.

      Dont disable cluster services in services.msc, pausing the node is equivalent to shutting down the node (i.e resources will not failover to other node)

      Regards,

      SBK