Former Member
Jun 30, 2011 at 11:56 AM

PR generated from MRP has wrong delivery date.

254 Views

Hi,

We use VB & HB setting for a material in MRP view.

After running MRP on 28/06/2011, the PR was generated with the delivery date as "07/07/2011".

The GR processing time in material master is maintained as 1 day only.

There is no info record available for this material.

Purchasing lead time in MRP parameters is also maintained as 1 day.

We have source list and we follow scheduling agreement/schedule lines process.

We assign this PR thro' ME57 to create schedule lines and the same is mailed to the vendorthro' ME9E. Due to the delivery date indication, vendor has not supplied the material. After facing stock out situation, we have found this "delivery date" problem.

On an average, we buy about 50000 materials thro' this route only for the past 3 years. This is the first time, we face this problem.

I need to fix this issue before I get similar issue with other materials.

Please let me know how to fix this issue.

Regards,

Siva