Define new JIT Sched. Indicator in purchase view of material master

Former Member
0 Kudos

Hi All,

I need to define new JIT Sched. Indicator. Where can it be defined and whats the path????

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

It is not possible to create new JIT delivery schedule indicators. SAP provides only folloiwng options;

	No JIT
1	Automatically

To check this, go to SE11 - Data Element "FABKZ", Double click on Domain "FABKZ", Go to Value Range Tab and see the fixed values.