I have planned inventory status (yellow status) created for the Bins. (LAGP- IVIVO). I can not create new physical inventory for this Bin. I am getting an error message- u201Cstorage bin already proposed for inventoryu201D

There are no stocks in the Bins and for some of the cases, even though there are stock in the bins, there are no pending inventory documents. But still there is yellow traffic triangle. Can anybody advice me, how to remove planned inv active (yellow) flag from storage bins Ls03n record?

Thnaks,

Milind

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 30, 2011 at 07:24 AM

    Hello Milind,

    It's difficult to say how this issue occured in the first instance but you have an inconsistency now in LS03n. The recommended

    approach would be to open an OSS message for SAP Support to logon and correct the table entry. Component LE-WM.

    I hope this information helps!

    Regards

    Martin

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Arakish,

      Yes you right. When the inventory status is planned, there is pending inv document for it. I found out the resolution.

      Yellow flag is automatically set by the system to make sure no two/multiple Inventory record exist for the same bins

      (1) Just enter the Bin number in LINK/LINP table and find out the Inv record. The status should be cleared. If status is not cleared then we have to complete the PI procedure for the record. Then yellow flag from the Bin master LAGP-IVIVO will automatically removed.

      (2) Another option is -


      if we are very sure about the Bin stock and no TO is pending to confirm for the Bins, we can simply delete the INV record of the Bin. Yellow flag from the Bin master record, LAGP-IVIVO will be removed.