Hi PP Gurus,
We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines
It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.
We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.
Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?
Thanks & Regards,
Sandesh
Hi Sandesh,
Is this happening for particular materials or for all materials
Couple of checks -
1) Check with material master changes, might be after MRP run PDT is updated in material master etc ..
2) Check in OPPQ, for option external procurement , whether scheduling info records/agree is marked or not
Best Regards
K.Madhu Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you maintain the PDT in Purchasing info record in ME11 or Material amster MRP2 view. Check and Revrt,
Santosh Sarda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.