Plannned Delivery time not considered while calculating delivery date

Former Member
0 Kudos

Hi PP Gurus,

We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines

It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.

We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.

Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?

Thanks & Regards,

Sandesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sandesh,

Is this happening for particular materials or for all materials

Couple of checks -

1) Check with material master changes, might be after MRP run PDT is updated in material master etc ..

2) Check in OPPQ, for option external procurement , whether scheduling info records/agree is marked or not

Best Regards

K.Madhu Kumar

Former Member
0 Kudos

Hi Sondesh,

If you are using purchasing info record to detrmine PDT, you also have to maintain taht perticular vendor in source list of material in ME01.

check and Revert,

Santosh Sarda

Former Member
0 Kudos

Hi,

I have just checked it and it is maintained as suggested and did MRP run but still it not considering planned delivery time

Please advice further.

Regards,

Sandesh

Former Member
0 Kudos

Hi,

Did you maintain the PDT in Purchasing info record in ME11 or Material amster MRP2 view. Check and Revrt,

Santosh Sarda

Former Member
0 Kudos

Hi Santosh,

We have maitained planned delivery time in materail master MRP2 view & we also have scduling agreement & sorce list for the vendor still it is not considring planned delivery time.

please advice further.

Regards,

Sandesh