Former Member
Jun 29, 2011 at 01:00 PM

Plannned Delivery time not considered while calculating delivery date

22 Views

Hi PP Gurus,

We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines

It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.

We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.

Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?

Thanks & Regards,

Sandesh