on 06-29-2011 7:57 AM
Hi gurus,
I have configured billing plan in my SD environment at Item Level.
I want to change it to header level.
Questions:
1- When I make the changes to update the system to have billing plan at header level for future sales orders, is that possible for me to change all my saved orders and open orders with the new settings so that I can also have those saved and open orders with a billing plan at item level?
2- If that scenario is not possible, could we for example copy the data of a previously saved or open sales order into a new sales order with the new customizing (Billing plan at Header level?)
Thanks for your input
Kind regards
Chris
Hi
I am afraid you cannot do that converstion for the existing orders. BP at header level are enabled at teh document type level, while BP at item level is done at item category. So both are independent. Mostly it is advisabel to use BP at item level only.
If you are already using item level BP, and want to mvoe to header BP, then only future transactions can be executed with BP at header level. Existing item level BPlans will remain so in the system.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.