In SRM4.0 ECS we have a peculiar issue.

1. PO created in SRM with account assignment (cost Centre & GL Account).

2. PO end up in "ERROR IN PROCESS" status.

3. In SRM backed PO in T-Code:BBP_PD is showing as ORDERED but also "Transfer Failed (E.Sys.)" status "I1132".

4. Such status occurs if there is error in account assignment

5. We have verified the existence & correctness of cost centre & GL account.

PO is hanging in SRM & not getting replicated to R/3.

Thanks & Regards.

Sandip.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 28, 2011 at 01:25 PM

    Hi Sandip,

    Pl check the error log in RZ20 for this PO to determine the exact cause and update here.

    Regards,

    Nikhil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Since it clearly says that the error is in Account assignment and you are confirming that things are ok in SRM, it would be worthwhile to investigate the system config in ECC. Take help of FICO consultant to verify config setings under SPRO in ECC. Ensure that cost centre has not expired

      Also I hope that customizing under following path is maintained correctly SPRO - SAP SRM - SRM server - Account assignment - Define G/L Account for Product Category and Account Assignment.

      Regards,

      Nikhil