In item details of PR where STATUS tab config settings will appear in SPRO

Hello,

Can any body please give suggestions for the following issues such as.......

Issue no 1: Date of PR created by requisitioner

And date of PR released status has to be populated in STATUS tab of PR.

Issue no 2: Date of RFQ created by purchase department against PR and Quotation

Received against RFQ from respective vendor and so on... status has to be

Populated in STATUS tab of PR.

Issue no 3: Date of Quotation send to sponsoring department from purchase department

For technical evaluation and again Quotation send back to purchase

Department from sponsoring department with appropriate comments and

Suggestions dates has to be populated in STATUS tab of PR.

So please let me know where configuration settings to be done.

Please treat this as a high priority issue.

Edited by: sapmm99 on Jun 22, 2011 3:55 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 22, 2011 at 06:19 PM

    Hi,

    You can try making the Date Field in Item Details and Requisitioner as Mandatory if it serves your purpose for the situation - I .

    Please check the following :

    SPRO>IMG>MM>Purchasing>Purchase Requisition>

    Click on Define Screen Layout at Document Level

    Highlight the Document Type

    Go to Details and click on Deadline Monitoring

    Check the Date as Required Entry for Requisition, Delivery & Release Date.

    ( The user will need to Enter Release Date Manually)

    Similarly this can be maintained for RFQ and PO as well.

    This will give you the Tracking of the Processing Time with respective dates.

    Hope this helps,

    Best regards

    Amit Bakshi.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 27, 2011 at 08:32 AM

    Hello,

    Can any body please give appropriate solution for this issue.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 27, 2011 at 08:34 AM

    this sounds pretty much like a modification, as you want modify a SAP standard tab.

    Usually one creates an own tab for all the data that you want see , this is achievable with a userexit then.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.