Language ZH is not installed in the system. Cannot activate Best Practice 1610 OP

Good day experts,

We loading SAP Best Practices for SAP S/4HANA (on premise) (U.S.A) (V3)

However on activation of the Solution: it generating the error:

Language ZH is not installed in the system. Cannot activate.

We have done:

SMLT (language management has been completed for English and German: DE)

2292425 - Removal of Language-dependent SAP Best Practice content.

However on this note, it maybe we did not follow the prerequisites correctly.

Can someone please assist? (please)

Regards,

Brandon

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Dec 15, 2016 at 08:31 AM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 04, 2017 at 09:17 AM

    Hi Prithviraj

    Apologies for the delayed reply.

    Thanks for your input. It helped.

    Regards

    Brandon

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 12, 2017 at 10:12 PM

    Hi Brandon,

    Can you explain the solution I am facing the same issue.

    BR

    Mandeep

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 13, 2017 at 11:52 AM

    Hi Mandeep,

    Please ensure the BP are installed/loaded correctly.

    Then follow the note: 2292425

    Regards,

    Brandon