What is the impact of missing MDRE(RMMDVM10)?

Dec 15, 2016 at 07:35 AM

104

avatar image
Former Member

Hi SAP MM Guru,

We set up planning file creation program (RMMDVM20) before MRP run batch job

RMMRP000 running in the background daily.

But the job of planning file consistency check RMMDVM10 is not set up for all plant.

May I ask what the implication is without the program?

Please kindly shed some light on this.

Thank you very much,

Sally

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Caetano Almeida
Dec 16, 2016 at 11:13 AM
0

Hi Sally

This program basically check for inconsistencies in the planning file. It will delete unnecessary entries and recalculate the low-level code when necessary. You don't need to schedule it as a daily job, but running it at least once a month would be nice, as it can help to speed up a little bit the MRP performance and make sure your materials are being planned in the right sequence.

Regards,

Caetano