Skip to Content
0

Double PR after MRP run for Crib Material

Dec 15, 2016 at 07:00 AM

24

avatar image

Hello

We have problems about MRP results of Crib materials. I checked the material master data and saw that everything seems OK.

For the example ref X.
Manuel re-order point is selected-VB

re order Quantity: 6 pc
Rounding value exist:6 pc

There is one PR which is in validation process: 0012925847 (therefore it is fixed-starred)

Acc. to MD04 screen , when the system receives 6 pc of the mentioned PR stock will be increased to 10.

MRP parameters:

Processing Key: NETCH Net Change in Total Horizon

Create Purchase Req.: 1 Purchase requisitions

SA Deliv. Sched. Lines: 3 Schedule lines

Create MRP List : 1 MRP list

Planning mode: 3 Delete and recreate planning data

Scheduling : 2 Lead Time Scheduling and Capacity Planni

Although this stock situation as I mentioned above why system is creating one more PR and increasing the stock to 16 after MRP run and how can I fix it?

Regards
Pinar

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

PINAR TEKİN Dec 15, 2016 at 07:04 AM
0
Share
10 |10000 characters needed characters left characters exceeded