Hi Experts!

I'm facing issue in releasing planned price for a material; for which the current status in period is "Quantities and Values entered".

When i try to release planned price system issues following message:

Price changes for material 6999 is not possible

Message no. C+811

Diagnosis

You want to change the price or release planned prices for material 6999 with valuation type in valuation area 1000. You have, however, already entered actual data or performed a single-level price determination in the period concerned. The status of the material in the period is Quantities and Values Entered.

Price determination indicator 3 assumes that the standard price remains constant throughout the period, so that all movements can be valuated preliminarily with the same standard price. Therefore, you can only change the standard price at the beginning of a period (i.e. as long as no actual data was entered).

System Response

The system does not allow the price changes or the release of planned prices for this material in this period.

Procedure for System Administration

In the future, to automatically release your planned prices upon creation of new actual data you can allow dynamic price release in Customizing for Actual Costing/Material Ledger.

Now Issues is that; I am unable to process billing document; as system tries to find "Active Cost Estimate"; which i cannot release due to above issue.