Hi friends

We have a sale order and a service order is assigned to it. Service order has the cost element 402601.

In OKGB, we have he setting as below

CO Area - 1000

RA Version - 0

RA Key - ZCS02 (which is assigned in SO)

Masked Cost element - 00004026++

Req to cap - ECS (Line ID)

And we have the below settings in OKG4

CO Area - 1000

RA Version - 0

RA Key - ZCS02

Req to cap - ECS

WIP 991106 991106 0,00

Reserves 991206 991206 0,00

COS/Revenue 991306

When we do the RA , it should select the CE for reserves - 991206 but this is not working and its selecting all cost elements defined in OKG4 for the below combination

CO Area - 1000

RA Version - 0

RA Key - ZCS02

Thus it is ignoring the Line ID ECS.

Can you pls let me know what may be reason for this.