on 06-17-2011 8:03 AM
Hi All,
There is an issue with Quanitity Display when I run MS02 for A material, the result doesn't show appropriate Quanitities.
I have a material Child1 which has Base Uom KL.
BOM Quantity is maintained in Litres in BOM.
It has parent XYZ and Bom is 1.25 L for 1000 KG of XYZ.
Now If I give PIR for XYZ and run MRP for Planning Scenario it gives the quantity of ABC as 0.002 KL which is wrong, It should have given 0.00125 which should round of to 0.012.
I have checked CUNI for UOM and maintained Decimal place as 3.
I cannot change the Base Qty for Material ABC.
Please suggest if there are any solution
Do you configure KL in your system? I don't think the standard SAP provide you with this. Please check the KL in CUNI, it should be the same with M3 (except the primary code should be unflag). In standard SI unit provided by SAP, 1000 L equal to 1 M3.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This is always recommended that in Material master Base UOM should be shortest one whatever you use. As in your case it should be either L or ML. Please try with this and revert back.
Regards
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.