Hi All,

I have scenario where the raw material "X" has Order reservations in past let us assume month as May'11. The Procurement time is 10 days and GR time is 2 days and the Lot Size is EX. When we run the MRP in month of June the PR which will be created for Order reaservations will have the "Purchase Requisition" scheduled Forward with release date maintained as the current date and the delivery date as 10 Working days ahead of release date and Requirment date will add 2 more days. And This Requirment date will be displayed in MD04 in Date column. let us assume that we have excuted MRP on 17-June, then for all Past requirments the release date willl be 17-june and Delivery date will be 01-July and Requirment date will be 05-July based on setting said above (Rem: - Saturday and Sunday is holiday).

Client does not want to see the requirment date planned this way. He wants the date in MD04 for PR to be maintained in Past only.

is there any way to make this happen?

Edited by: ANIMESH KUMAR on Jun 17, 2011 7:45 AM