Skip to Content
0
Jun 16, 2011 at 08:04 PM

DMR - Change Current Inspection Stage

381 Views

Hi,

I have set up Dynamic Modification at my client and it is working as expected but there are situations where the users want to manually change the inspection stage in the inspection lot. Is there a way to do that? I know I can change the next inspection stage manually in the quality level prior to the PO receipt but cancelling and reprocessing the receipt is not feasible and the warehouse, which processes the receipt, isn't involved in the QA process.

Is there a FM I can use ?

Thanks,

Alas84