Hi
I have a work center for external process and a control key created for external as well. In setting up the control key I choose "automatic goods receipt" and "confirmation required".
Then I have 2 semi parts A and B. Same routings are created for them with the work center and control key mentioned above.
When I create production orders for A and B, I can get a purchase requisition for external process and convert it to a PO. Further when I make a goods receipt to the PO, the production orders are marked with status "CNF". What's surprising me is only for part A the goods receipt of production order is done automatically when the PO is done with goods receipt. No "DLV" for the B production order.
I compare the material master of A and B - can't see any difference...
Please give me some suggestion on where I should look into. Thanks a lot in advance.
yu