Hello PP-Pro's!

I would like to switch of assembly production in our company and simply work in an MTO-environment. Thus when I create a sales order, it will execute an MRP-run and create a planned order automatically.

Perfect - but the planned order does not create any capacity requirements. The general settings for the planned order seem to be ok - so if I enter it and execute scheduling, the capacities are created. Also if I execute MD50 it is working as required.

The parameters in OPU5 are looking alright to me - so any hints how I can make SAP to execute a capacity req check when the requirements from the sales orders are creating a planned order through MRP?

Any hint is highly appreciated...