Hi All,

In Subcontracting when we do Transfer posting of Child components to SC vendor at ME2O, the Purchase order number is not storing the material document.

As a result of this at the time of MIGO I am not able to assign the Challan. The ssytem throughs an error" Challan Material is differnet from the material document"

If I do the transfer posting at MB1B the PO number is getting stored in the material doc. hence also i can assign the challan at MIGO.

My client wants to use ME2O. They don't want to use MB1B..

If I use ME2O for Transfer Postings then in the material doc resulted with that transfer posting will not contain the PO number.

Hence I am not able to assign the challan created with that mat doc at the time of GR.

Can any body tell me how correct this issue.

Thanks in Advance.