on 06-15-2011 8:47 AM
Hi Experts,
In project i m using a user status for taking approval / release budget .
Description Lower Highest
initial 1 2
bud planning 2 3
bud release 3 4
release 4 5
execution 5 5
Here, after getting approval / Release budget i have to change staus manually (based on authorization).
Now here i want that when i add supplement budget then once again system should go on bud planning and authorized person change the status (from bud planning to bud release).
For this in OK02 i had set Bud Supplement on Bud Planning. (According to that while budget is supplement then status go back on bud planning).
Here i m little bit confused that wt level i have to select here between lower and highest. (i m taking the same level as shown above)
While testing this, i m not getting the required ans..
pls suggest me if i m doing something wrong.
Regards,
Hi Narender,
can you please explain what you want from user status.
Thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Description Lower Highest
initial 1 2
bud planning 2 3
bud release 3 4
release 4 5
execution 5 5
Please understand this, if you want to move form bud release to bud planning, then lower limit of bud release should be 2 not 3.
as per your settings system would not move from one status to its previous status.
Lower limit is what ever the status number it scan move backwards, understand this basic concept & apply it as per your requirement, I have just explained one scenario here.
Thanks
SL
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.