Former Member
Jun 14, 2011 at 06:41 PM

operation splitting

110 Views

hi,

any body please help. I am having three issues in operation splitting. please suggest me how to solve these issue. my scenario is make to stock and discreet manufacturing and every routing having minimum for operations.

issue 1) first operation i have confirmed 100 qty. but in second operation i want split as per capacity. if capacity is available i will go in normal process else i want to split in to two or three and i want assign work center and qty as per the capacity available. and the 3rd operation is again full qty and single work center. how can i configure this.

issue 2) once i split the operation how can i reschedule the date.

issue 3) once i confirmed operation in partial qty. during remaining qty confirmation due to machine break down how can i change workcenter to that operation for remaining qty.

please suggest me solutions.

thanks & regards

Bhakta