Hi
In OPU3 i maintained automatic scheduling.
If we have 8 operations in one production order.
after first operation is confirmed with actual deviation date ie as per routing its 50 min actually its taken 70 min.
so remaining operation s to be reheduled automatically after preceeding operations are confirmed.
Presently when we are going to Co02 then after clicking schedule order only its rescheduling..
we want this automatically Is it possible.
Regads,
srihari.M