Determine Task

Dear Experts,

I'm new in Plant Maintenance Module, I still confuse about "Determine Task" in create maintenance plan for preventive maintenance. Any one know how it use?

thx for the answer

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Jun 14, 2011 at 11:14 AM

    You can automatically determine (create) tasks based on the Priority setting in the notification header.

    These settings are made in the IMG

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 14, 2011 at 11:27 AM

    Hi,

    As Pete told, this setting will be done in IMG.

    Follow this path:

    IMG => PM & CS => Maintenance & Service Processing => Maintenance & Service Notification => Notification Processing => Response Time monitoring => Define response monitoring

    In Response Profile, under response times, for the priority selected in maintenance plan, tasks will be assigned. That will be called in notification automatically if you tick that check box,

    Regards,

    Maheswaran.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 14, 2011 at 05:47 AM

    Hi,

    I couldn't trace your link. Can you tell the path?

    Regards,

    Maheswaran.

    Add comment
    10|10000 characters needed characters exceeded