Dear Experts,

I'm new in Plant Maintenance Module, I still confuse about "Determine Task" in create maintenance plan for preventive maintenance. Any one know how it use?

thx for the answer

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

You can automatically determine (create) tasks based on the Priority setting in the notification header.

These settings are made in the IMG

PeteA

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As Pete told, this setting will be done in IMG.

Follow this path:

IMG => PM & CS => Maintenance & Service Processing => Maintenance & Service Notification => Notification Processing => Response Time monitoring => Define response monitoring

In Response Profile, under response times, for the priority selected in maintenance plan, tasks will be assigned. That will be called in notification automatically if you tick that check box,

Regards,

Maheswaran.

Former Member
0 Kudos

oke thanks for the answer, this is very helpful

Regrads,

Bernardus Jalu

Former Member
0 Kudos

Hi,

I couldn't trace your link. Can you tell the path?