Skip to Content
0
Former Member
Jun 14, 2011 at 02:40 AM

How can Change PO Release Indicator to Released Status

740 Views

Hi Gurus,

We are having an issue here, which user accidentally re-triggered customized program to re-trigger the release strategy of old PO documents.

This program basically reset the PO release startegy status and update the PO with the latest PO release strategy configuration. It's using FM ME_REL_STRATEGIE_EKKO.

So, currently some of the old PO which previously been fully released and closed PO (with GR & IR completed). So, we dont think that it's right for these old PO to be approved again, also the relevant approvers also refused to do so.

Is there any way that we can use the same FM to change the release indicator to R from S? Appreciate your help. Thanks!

Regards,

Michelle