Hi All,
I have a situation where i have to write an Object Dependency to change the setup time of an operation based on the length of the material selected by the customer.
For the first 5 inches, the Setup time should be 4Hrs, for each additional 5 inches the Setup time should be increased by 1Hr. there is no limit on the length they can select.
I have created a Reference Characteristics SETUP_TIME, and have a Characteristic called LENGTH. I could use some help with writing the dependency.
Thanks for the help.