We are running CK40N for this month. But we are getting an error like this:

No cost field for fixed costs has been defined

Message no. CK256

Diagnosis

The cost rollup resulted in a cost element containing fixed costs that cannot be assigned in cost component structure 31 because cost component 001 was only defined for variable costs in Customizing.

System Response

The fixed costs for the cost element can be neither assigned nor rolled up.

When I checked the cost component structure, item 001 - Material cost is having only "variable costs". I dont understand from where this fixed cost is coming ? Material cost is coming from the material master data values, right ? Where we have entered a fixed cost value for material cost element, I am not getting. (Is it KP06)