Hi,
Finished item A is maintained plant 1000 . Special procurement key is 40 (stock transfer from plant 1100) and strategy 40. Material B is maintained in plant 1000. Strategy 40 and inhouse production.
Material A has BoM of B in plant 2000. Qty is 1: 1 ratio. A and B has strategy 40.A is inhouse production but B has special procurement key of 41( stock transfer from plant 1000)
Requirement is to have sales order for A in plant 1000 . STO for A triggers to plant 2000. Another STO triggers for B to plant 1000 from 2000. But the quantity of B gets clubbed in STOs if there are 2 sales orders in plant 1000 for A for same delivery date. I want separate STOs for individual sales orders.
Kindly guide.
Thanks.