Skip to Content
0
Former Member
Jun 10, 2011 at 09:00 AM

Correct posted document with right WBS

40 Views

Hello,

There is some inconsistency in asset and inventory report because there is 2 PS documents that was created (via CJ8G) with a WBS which was deleted after the creation of these 2 documents.

Now after WBS deletion, the documents have no value in WBS element field !

I do not succeed to know how this WBS was deleted despite the fact that there are already 2 open documents assigned to it.

But now the problem is how to correct these 2 accounting documents with new WBS element to have correct values in the report ?

Is there any transaction to correct PS document to update WBS element ?

Thank you