Hi,

We are creating a production order for Billets that is our Semifinished goods. The material master is maintained at Std price.

Lets say that Std prce of the Billet is 100.

Lets say that after the production order is completed , the actual cost of Billet is comes out to be 125.

Now this billet is used for the production of the finished goods Wires. For the production order of wires, the price of the billet is taken as 100.

In this way the actual cost of the Wire will not come.

May be this is the standrad process. Let me know in any way can we use price difference of 125-100= 25 in the production cost of wires so that I can get the actual cost of the wire.

We are not using Material Ledger.

Any suggestion

regards