Purchase requisition material price

214 Views

Hi all

My understanding is that the valuation price of a material (In my case MAP) is defaulted into the purchase requisition valuation price.

I have a bit of a funny scenario here.

I have a plant WB00 (requesting plant - no stock is kept in this plant) (we manually update the MAP for release purpose on the PREQ)

I have another plant (SWB0) (Supplying plant - this plant holds stock and seen as vendor. Requsting plant will create order against this plant).

I have now activated Split Valuation on plant SWB0.

I have the following

Material 1 - SWB0 - Val Type "" - R200

Material 1 - SWB0 - Val Type New - R300

Material 1 - SWB0 - Val Type Reclaim - R100

Material 1 is in Plant SWB0 and Sloc WB52.

On Plant WB00 there is no Split valuation.

In the account view of Material 1 in plant WB00, the MAP price is R300.

When I create the PReq for this material and enter the plant WB00, the price comes as R300.

However when I put in the Sloc WB52 o nthe preq, it then changes the price on to R200.

I require it to stay at R300. What could I be doing wrong.

Thanks