HI Guru's

This is regarding Confirmed date in the sales order.

In MMBE, enough stock is availble in unrestricted use stock.

I have created a sales order where the req delivery date is on 9/06/2011.

But in the schedule lines, system is displaying 2 delivery dates where the 1st line with today's delivery date is not confirmed

where as in the 2nd line, delivery date is displaying as 21.06.2011 with confirmed delivery date.

1. kindly let me know why system is displaying 21.06.2011 and why it is confirming on 21st.

Iam tring to test in IDES.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Check in MD04 to see if there are any other demands generated for the material you have used in the sales order?

This could be one reason why the order is not confirmed on the same day.

Regards,

Ram

Former Member
0 Kudos

Hi ,

Check in sales order type in VOV8 for Lead time in days.It should be blank.