Hi,

We have defined a BOM like below:

For 1000 kg of header material 5.556 EA of material X is required.(Material X is packaging material is always available in inventory in intergers.

Now I have created a process order of 180 kg. System propose required qty of material X as '2'.

System has done calculations as below = 5.556/1000*180 = 1.00008.

My requirement is that in this case system should proposerequirements of 1 EA instead of 2 EA.

Q- How to do that?