Jun 08, 2011 at 03:59 PM

Production orders rescheduling when revoking TECO

106 Views

We automatically (COHV) set all our production orders to TECO status after a certain period. Sometimes users have the need to revoke that status, for example to be able to reprint the orders. When revoking TECO and saving the orders, the dates are changed (both basic and scheduled finish dates change to the start date).

Why is this happening, and is there any way to lock these dates into place?