Dear All,
We have one issue regarding the Finish Stock transfer from Excisable Plant A to Non Excisable Plant B.
Standard Costing is implemented.
Material X is maintain on Standard Price S.
Example
Material X cost in Plant A = 100
Material X cost in Plant B = 150
Material X production is done in both the plant.
When we transfer the material from Plant A to Plant B we have to add the excise duty to material cost when we received in Plant B as Plant B is non excisable so all cost should be added to material cost.
Plant A Material X cost = 100
Add: Excise Duty = 10 Rs
Total Cost will be 110 Rs
So system is debiting the Material in Plant B for Rs 150 instead of 110Rs. and balance transfer to Price difference. This is because of Standard price indictor maintain in Material Master.
Client is not accepting that .
Is there any solution for that .
Regards,
Shayam