Budget in internal order assigned to WBS

477 Views

Hi Experts:

I have projects with two levels. Second level WBS elements have internal order assigned. I can't change it because of MM requirements. I would like to have availability control in my WBS elements and in my internal orders . However, the system issues a mistakes when you try to assign buget to internal orders assigned to WBS elements.

According to that mistake, internal orders assigned to WBS elements can not have budget because the budget is provided from the WBS element.

I know I can plan internal orders and spend budget when I plan them but it is not exactly that I need.

Would it be possible to make something about that?