I have changed status of wbs to TECO and this wbs is already assigned to network activity that has an existing requisition(PR)/PO in it.

now after doing TECO STATUS for wbs, again i went in network activity and tried to create new purchase requisition(PR) on same activity it is allowing to create new PR.

Can some confirm me whether it is an error or as per standerd of SAP it is correct.