Dear All,
I have a general query regarding Resource networks ( Newly added functionality in SCM 7.0 ) if anyone has worked on it.
Is it possible to include alternate resources in resource network.
For e.g. Say I have 2 machines M1, M2 feed to 3 distillers D1, D2 & D3.
M1 can feed to D1 or D2 depending on the availibility. However M2 can feed only to D3.
Can we have the first relation defined in a single resource network M1 ---> D1 OR D2.
OR
I need to have 2 resource networks defined:-
1. M1 --> D1
2. M1 --> D2
Thanks in advance for your help
Regards
Ameet