Set up cost in production order

825 Views

Dear Experts,

My client want to track Setup cost separately in production order .

I am already using machin,labour and power as activity for capturing production cost.

If i will create set up as activity and same i will defined in routing as well with qty and rate.So my setup cost will be credited at production order confirmation.but my actual cost of set up.How i will differentiate.

Means- set up actual cost are labourpowerdep.

But depreciation coming as whole amount in prodction cctr under one GL.How to break set up Dep and Machin DEp.

Same with Power- ooked under one GL.How to break setup power and prodction related power

and same with labour.

How to track set up cost