Skip to Content
0
Jun 07, 2011 at 06:30 AM

weighted Average : Progress Analysis

73 Views

Hi Experts,

My clients requirement is weighted average of activities at WBS level.

I am getting confuse for formula of weighted average. For example

IF Under WBS 1 there is 2 Activities A1 and A2.

POC of current month For A1 & A2 is 40% & 30%

Weightage for A1 & A2 is 70 & 30

then At the level of WBS1 what figure should come?

I am seeing progress in CNE5 report.

Please suggest me.

Thanks in advance