Using Kanban to post to post to a cost center

453 Views

Scenerio:

PK05 - Supply Area ABC is set up for Storage location 3020.

OM13 - 0007 Defined as control type 1 Stock Transfer with reservation

- Immediate to Crtn checked

- Cons Cost ctr set to 2 Procurement for cost center

PK02 - Material 123-4567 is tied to Supply area ABC.

- Stock transfer Type = 0007, Storage Location = 3010, Supply Source = SA

- tied to cost center 20210

When the Kanban is marked as empty, no changes happen to inventory. This is what we want to happen at this point.

When the Kanban is marked as full, cost center 20210 is charged the correct quantity, but there is a quant with a bin number 0000020210 (the cost center number) for the (negative) quantity of the Kanban (ex -10). There was sufficient quantity in the SA quant.

What do I need to change to make the negative quant automatically be filled by the SA Supply Source?