Hi all,
I have a scenario where we are producing a semi-material and as a normal process the produced material comes out with different quality grade such as A Quality Material, B Quality Material and C Quality Material.
- The stock for all these different quality materials is maintained separately.
- The A Quality Semi-Material can only be used in producing A Quality Finished, B Quality Finished must use B Quality Semi Finished, and C Quality Finished must use C Quality Semi-Finished material from stock.
- The valuation for different quality materials is different and we are using Material Ledger.
- The selling price for different quality materials is also different.
Can anyone please tell me how this scenario will be best managed in SAP ECC 6.0?
Thanks!