Maintenance plan scheduling

80 Views

Hello Guys,

I have a maintenance plan with shift factors early/late set to 100% to adjust the schedule automatically based on the previous completion of work order. Lets say itu2019s a weekly activity created work on 1st of May 2011 and next order is scheduled for 7th of May 2011. Now If I complete my first work order on 4th of May 2011, I am expecting my next work order to be created only on 11th of May instead of 7th of May due to shift factors setting to 100%.

My question is, if I have a background job running every week ( in my case 1st of May )thru IP30 with interval call object as 7 days, work orders for the next 7 days will be created ( till 7th of May) prior to week. In this case I have my next work order created already prior to one week. So if I complete my first work order on 4th of may, how the system adjust the schedule as work order is already created?

Mahee