Dear experts,
I would like to create Network Activity with BAPI_NETWORK_MAINTAIN for EXTERNAL PROCESSING TAB, please see the following for the sample data which I filled in 'Test data directory'.
When I execute, I got the Error Message 'Enter activity quantity and base unit of measure' in structure E_MESSAGE_TABLE, but I cannot find these fields in the I_ACTIVITY structure, please advise how can I solve this problems....
By the way I had saw some user defined fields in the structure I_ACTIVITY such as: USER_FIELD_KEY,USER_FIELD_CHAR20_1, USER_FIELD_CHAR20_2,...., USER_FIELD_FLAG2.
Can I apply these fields to solve my problem? If yes, please give me some sample code...
Ps. I have used the control key: PS02, 'coz it's mean 'external process'.
*-----I_METHOD_PROJECT
REFNUMBER 000001
OBJECTTYPE NETWORKACTIVITY
METHOD CREATE
OBJECTKEY 0000040001200030
REFNUMBER
OBJECTTYPE
METHOD SAVE
OBJECTKEY
*-----I_NETWORK
NETWORK 4000120
*-----I_NETWORK_UPDATE
NETWORK X
*-----I_ACTIVITY
NETWORK 4000120
ACTIVITY 0030
CONTROL_KEY PS02
PLANT 1001
DESCRIPTION ACTIVITY 30
VENDOR_NO 10000003
PRICE 5.00
PRICE_UNIT 1
COST_ELEM 6136808
CURRENCY EUR
CURRENCY_ISO EUR
PURCH_ORG 1001
PUR_GROUP 001
MATL_GROUP 10001
PROJECT_DEFINITION Z/019
WBS_ELEMENT LEVEL-00.11
OPERATION_MEASURE_UNIT EA
OPERATION_MEASURE_UNIT_ISO EA
*-----I_ACTIVITY_UPDATE
NETWORK X
ACTIVITY X
CONTROL_KEY X
PLANT X
DESCRIPTION X
VENDOR_NO X
PRICE X
PRICE_UNIT X
COST_ELEM X
CURRENCY X
CURRENCY_ISO X
PURCH_ORG X
PUR_GROUP X
MATL_GROUP X
ACTIVITY_COSTS X
PROJECT_DEFINITION X
OPERATION_MEASURE_UNIT X
OPERATION_MEASURE_UNIT_ISO X
Thanks in advances,