Internal orders commitment lines KOB2 are not getting updated

Created Purchase Order with two lines and account assignment group F

One line gave the material and another line gave the description only.

Assigned internal order number for both (in IO commitment has been checked)

When I save the PO in KOB2 commitment lines I could able to see the expense line details only not the details of the line entered with Material.

Can any one please help

Thanks,

Sudha

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 01, 2011 at 07:31 PM

    Hello Sudha ,

    I agree with Alex. Value-based commitment indicator has to be set.

    I wanna add two notes:

    634298 FAQ: Commitment update in the service

    433597 Commitment update for services or invoicing plan

    If you need to correct commitments, you can use RKANBU01 (as described in note 152571)

    Cheers,

    Lucas

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 01, 2011 at 06:46 PM

    Hi.

    check commitment do in PO directly,may be you didn't maintain cost element or something else

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.