Jun 01, 2011 at 09:55 AM

Do we need to match KP06 and KPZ2?

184 Views

Dear Experts,

I understand that KP06 can do the planning by a combination of 'cost center' and 'cost element', and whereas KPZ2 can plan by 'cost center' only.

Say the following are the example of the planning in KP06.

Cost center 101 and cost element 222 = $1000

Cost center 102 and cost element 222 = $2000

Cost center 103 and cost element 222 = $3000

Cost center 101 and cost element 333 = $500

Cost center 102 and cost element 333 = $1500

Cost center 103 and cost element 333 = $2500

My question is, do we need to match the total cost (in cost center wise) we planned in KP06 with the cost planned in cost center wise in KPZ2?

In my example will be :-

Cost center 101 = $1500

Cost center 102 = $3500

Cost center 103 = $5500