Dear experts,
i have a bit of a basic question, however due to problems with my SAP sanbox, I cannot test this myself.
I have a sales Bom for Finished good A, the components in the sales BOM are B and C
I have independent requirements in SAP for article A
When I run MRP, MRP will schedule purchase requisitions to match de independent requirements for article A
My question is, when running MRP (MD02), will MRP also calculate the dependent requirements and source stock for components B and C in order to meet the forecasted demand for article A?
Is there a particular setting that needs to be set up in order to make sure that all dependent requirements from the sales BOM are also exploded and sourced by MRP?
Your input is much appreciated!
M