SNP & DEPLOYMENT HEURISTICS

213 Views

Hello Everybody

I am currently working on a solution where SNP Heuristics run with a Frozen horizon (SNP PRODUCTION & STR) of 8 weeks & the Deployment is done based on a Pull Deployment & Push Deployment Horizon of 180 days. Does it make sense that we are confirming the plan for 8 weeks & deploying accross 180 days?

Best Regards

Mukta