Hello,
I want to use co-products in a production order with the following apportionment structure:
Material X: 95 (principal material)
Material Y: 5 (co-product)
In the production process, the actual ratio produced however is 90-10!
I have the following questions:
1) Upon settlement of the order, is there a way in which SAP can reflect the real apportionment (90-10) instead of the one
defined in the material master (95-5)? Is there a config or user-exit one can use to accomplish this?
2) What unit of measure is SAP taking into acount in the aportionment structure? Base unit of measure?
Thanks for any reply.
Aart